COVID-19

Click here to learn more about how UDOT is responding to COVID-19 

Access to 7200 South and I-215 is changing for drivers on northbound I-15 in late 2020. Click here to view an illustration of how to access these two locations from northbound I-15. 

Construction Update  - Nov. 20, 2020

The following construction activities and associated traffic, pedestrian and residential impacts are located along northbound I-15 in Midvale, Sandy and Draper cities. 
Note: Construction activities and schedule are subject to change.

CONSTRUCTION HIGHLIGHTS 

Northbound I-15 in Sandy

Expect Heavy Delays This Weekend – Crews will reduce I-15 to two lanes between 11400 South and 9400 South from 9 p.m. on Saturday, Nov. 21, through 5 a.m. on Monday, Nov. 23. Delays are estimated to be at least 30 minutes, especially during the day on Sunday, Nov. 22. Drivers are encouraged to plan extra travel time or avoid the area. Construction activities are weather-dependent and subject to change.

Catalpa Street in Midvale

On Monday, Nov. 23, and Tuesday, Nov. 24, drivers can expect daytime traffic shifts and one-way flagging on Catalpa Street between 7385 South and 2nd Avenue. This will allow crews to conduct utility work in the area.

Monroe Street in Sandy

Now through early December, expect work on Monroe Street between 9400 South to 9000 South as crews complete activities such as installing driveways, sidewalks and curb and gutter. Drivers should expect traffic shifts and one-way flagging.

Thanksgiving Schedule

Next week, there will be no traffic impacts from Wednesday, Nov. 25, at noon, through Monday, Nov. 30, at 10 p.m. Construction work will be limited during this time.

The I-15 Northbound team wishes everyone safe travels and a happy holiday season!

other projects in the area

New Project at 9000 South at Monroe Street Intersection in Sandy

A new project is scheduled to begin in early November at the intersection of 9000 South and Monroe Street. If you would like to receive updates about this project, please contact the project team by calling 855-740-8740 or emailing 9000smonroe@utah.gov. For more information, you can also visit the project website at udot.utah.gov/go/9000smonroe.

What to Expect BY LOCATION

 

Northbound I-15: Bangerter Highway to 7200 South 

  • Narrowed shoulders.

  • Daytime and nighttime lane closures on mainline I-15.

  • Daytime and nighttime lane closures on interchange off-ramps and on-ramps. The ramps will remain open to traffic during lane closures.

  • Express Lane converted to a general purpose lane.

  • Site preparation activities, which include:

    • Installing utilities and drainage.

    • Clearing landscaping and dirt.

    • Removing the concrete barrier.

    • Installing temporary barrier and fencing.

    • Saw cutting.

    • Concrete grinding.

Midvale: 7200 South to Copperview Park

  • Catalpa Street: Lane shifts and one-way flagging between 2nd Avenue and Millennium Way, day and night. (Not shown on map.)

  • Center Street (7720 South): Bridge work is ongoing. Lane closures day and night between Main Street and Chapel Street. The north sidewalk is closed and pedestrians will be detoured to the south sidewalk. Flaggers are stationed on the south sidewalk as needed.

  • Oak Street: Daytime road closure on the south curve, just west of Chapel Street. Sidewalk closure and pedestrian detour in place day and night. 

  • Wasatch Street (8000 South): Bridge work is ongoing. One-way flagging between Allen Street and Chapel Street day and night.

  • Adams Street: Day and night work continue in this area for activities associated with the Collector-Distributor system. Noise wall installation has begun near the Wasatch Street bridge.

Sandy: 8600 South to 11400 South

  • Harrison Street: Pedestrian detour continues to be in place for sidewalk reconstruction. 

  • 9000 South Interchange: Utility and road work are ongoing. Nighttime lane closures on the northbound off-ramp and on-ramp.

  • 255 West: Permanent road closure between 9000 South and Monroe Street.

  • Monroe Street:

    • One-way flagging and lanes shifted from 9400 South to east of 255 West, day and night.

    • Sidewalk closure just south of 255 West.

    • Lanes shifted on Monroe Street and 300 West, both near 9400 South. All lanes open during peak commute times.

    • Southbound lanes shifted from Town Ridge Parkway to the Mountain America Credit Union building. (Not shown on map.)

  • Cross Streets: Nighttime lane closures on 9000 South (shown on map) and 10000 South, 10600 South and 11400 South. (Not shown on map.)

Draper: 11400 South to Bangerter Highway

  • State Street: Lane closures day and night between 11900 South and 12150 South.

  • Minuteman Drive: Daytime and nighttime lane closures, lane shifts, narrowed shoulders and one-way flagging between 12450 South and 13200 South. Flaggers will be stationed at various locations on Minuteman Drive to assist with traffic flow and business access.

  • Cross Streets: Nighttime lane closures on 11400 South and 12300 South. (Not shown on map.)

What to Expect Project-wide

​Drivers, residents and businesses can expect the following during construction:

  • Day and night work

  • Noise, dust and vibrations

  • Construction lighting at night

  • Construction vehicle traffic

  • Traffic shifts

  • Lane closures

  • One-way flagging

  • Road closures and traffic detours

  • Sidewalk closures and pedestrian detours