COVID-19

Click here to learn more about how UDOT is responding to COVID-19 

CONTACT US
HOTLINE
801-747-9950
EMAIL

Construction Update  - Sept. 11, 2020

The following construction activities and associated traffic, pedestrian and residential impacts are located along northbound I-15 in Midvale, Sandy and Draper cities. 
Note: Construction activities and schedule are subject to change.

CONSTRUCTION HIGHLIGHTS 

I-15 Northbound Lane Restrictions in Sandy and Midvale

On Saturday, Sept. 12, a single left lane closure will be in place on northbound I-15 between 10600 South and 8000 South from 6 a.m. to 6 p.m. while crews work in the median to install barrier.

On Tuesday night, Sept. 15, a single left lane closure will be in place overnight on the northbound I-15 exit ramp to I-215 while crews place temporary pavement and restripe the lanes. Beginning Wednesday morning, Sept. 16, drivers should expect a temporary lane configuration on the ramp as crews work to tie in the new collector-distributor system to 7200 South and I-215.

9000 South Full Closure in Sandy

On Saturday night, Sept. 26, crews will close 9000 South in both directions at I-15 from 9 p.m. to 8 a.m. while they pour the new bridge deck. (See detour map below.)

  • The following detours will be in place during the 9000 South closure:

  • Eastbound 9000 South through-traffic will be detoured to 10600 South via I-15.

  • Eastbound 9000 South traffic will still be able to access northbound and southbound I-15 during the closure.

  • Westbound 9000 South through-traffic will be detoured to 10600 South via State Street.

  • Westbound 9000 South traffic can access I-15 via 10600 South or 7200 South.

  • Northbound and southbound I-15 traffic exiting at 9000 South will be detoured onto westbound 9000 South.

OTHER PROJECTS IN THE AREA

126 South; Creek Meadow Road to State Street

UDOT began resurfacing this section of roadway in May 2020. If you have questions, you can contact a project representative at 855-740-8740 or 12600south@utah.gov. For more information about this project, visit udot.utah.gov/go/12600south.

What to Expect BY LOCATION

 

Northbound I-15: Bangerter Highway to 7200 South 

  • Narrowed shoulders.

  • Daytime and nighttime lane closures on mainline I-15.

  • Daytime and nighttime lane closures on interchange off-ramps and on-ramps. The ramps will remain open to traffic during lane closures.

  • Express Lane converted to a general purpose lane.

  • Site preparation activities, which include:

    • Installing utilities and drainage.

    • Clearing landscaping and dirt.

    • Removing the concrete barrier.

    • Installing temporary barrier and fencing.

    • Saw cutting.

    • Concrete grinding.

Midvale: 7200 South to Copperview Park

  • Catalpa Street: Lane shifts and one-way flagging between 2nd Avenue and Millennium Way, day and night. (Not shown on map.)

  • Center Street (7720 South): Bridge work is ongoing. Lane closures day and night between Main Street and Chapel Street. The north sidewalk is closed and pedestrians will be detoured to the south sidewalk. Flaggers are stationed on the south sidewalk as needed.

  • Oak Street: Daytime road closure on the south curve, just west of Chapel Street. Sidewalk closure and pedestrian detour in place day and night. 

  • Wasatch Street (8000 South): Bridge work is ongoing. One-way flagging between Allen Street and Chapel Street day and night.

  • Adams Street: Day and night work continue in this area for activities associated with the Collector-Distributor system. Noise wall installation has begun near the Wasatch Street bridge.

Sandy: 8600 South to 11400 South

  • Harrison Street: Pedestrian detour continues to be in place for sidewalk reconstruction. 

  • 9000 South Interchange: Utility and road work are ongoing. Nighttime lane closures on the northbound off-ramp and on-ramp.

  • 255 West: Permanent road closure between 9000 South and Monroe Street.

  • Monroe Street:

    • One-way flagging and lanes shifted from 9400 South to east of 255 West, day and night.

    • Sidewalk closure just south of 255 West.

    • Lanes shifted on Monroe Street and 300 West, both near 9400 South. All lanes open during peak commute times.

    • Southbound lanes shifted from Town Ridge Parkway to the Mountain America Credit Union building. (Not shown on map.)

  • Cross Streets: Nighttime lane closures on 9000 South (shown on map) and 10000 South, 10600 South and 11400 South. (Not shown on map.)

Draper: 11400 South to Bangerter Highway

  • State Street: Lane closures day and night between 11900 South and 12150 South.

  • Minuteman Drive: Daytime and nighttime lane closures, lane shifts, narrowed shoulders and one-way flagging between 12450 South and 13200 South. Flaggers will be stationed at various locations on Minuteman Drive to assist with traffic flow and business access.

  • Cross Streets: Nighttime lane closures on 11400 South and 12300 South. (Not shown on map.)

What to Expect Project-wide

​Drivers, residents and businesses can expect the following during construction:

  • Day and night work

  • Noise, dust and vibrations

  • Construction lighting at night

  • Construction vehicle traffic

  • Traffic shifts

  • Lane closures

  • One-way flagging

  • Road closures and traffic detours

  • Sidewalk closures and pedestrian detours